Pipes going in on Decebal: work has started on the road to the economic zone

Storm-drain work has begun on Decebal street in Ungheni — the first stage in rebuilding the 1,003-metre stretch leading to the free economic zone. Mayor Vitalie Vrabie visited the site on the morning of 3 July and pressed the contractor to pick up the pace, after asking it on 22 June to speed up the start. The total investment tops 25 million lei, and the works are promised for autumn.

TRIANGULATED Confirmed sources
▲ PEOPLE
Ungheni City Hall — official on-site announcement (Facebook post, 3 July 2026)
▲ DOCUMENTS
MOLDPRES — report on the signing of the works contract (13 March 2026) · Ungheni City Hall — Disposition no. 78-02/1-7 of 8 April 2022 (State Register of Local Acts)
▲ DATA
missing

We verify every story against 3 sources: people, documents, data.

Ion Calmîș
· editor
3 July 2026
Workers in hi-vis vests and an excavator unload large concrete storm-drain pipes on the shoulder of a road outside town; a field and the silhouettes of industrial buildings in the background.
Storm-drain pipes delivered along the Decebal street route towards the free economic zone, at the start of the works. Photo: Ungheni City Hall

Decebal street in Ungheni has moved into the works phase. The city hall says that on the morning of 3 July, installation of the storm-water drainage network began along the route — the first of the stages in rebuilding the stretch that leads to the free economic zone. “The rest will follow,” the administration notes.

This is the 1,003-metre section between the junction with Alexandru Cosmescu street and the one with Oleg Ungureanu street, in the Tineretului district — the part that provides access from the city to the “Ungheni-Business” free economic zone, one of the municipality’s busiest arteries. Along the 1,003 metres, the roadway is to be rebuilt, parking laid out, new gas and street-lighting networks installed, and an underground storm-water collection system put in — the part now getting under way. We covered the project, the money and its backstory in full when the works were announced.

A concrete storm-drain manhole set into a dug trench on the shoulder of Decebal street, with a pipe visible in the ditch; in the background, the road and a worker talking to a man in a white shirt.

The administration is pressing the contractor

The actual start came after Mayor Vitalie Vrabie held a meeting on 22 June with representatives of the contractor — the company SRL “Aedificator” — urging them to speed up the start of the works. On the morning of 3 July, the mayor returned to the site, where the contractor again gave assurances about the deadline.

Mayor Vitalie Vrabie, crouching by a concrete manhole ring, inspects the materials together with two workers in hi-vis vests on the shoulder of Decebal street.

The contractor gives assurances that the works will be completed by autumn.

Ungheni City Hall

The completion time set in the contract, however, is 11 months from the Work Commencement Order, according to the state agency MOLDPRES — longer than the “autumn” announced on the city hall’s own channel. The gap shows why a clear works schedule matters, which the administration says it has demanded.

What it costs and who pays

The rebuild is part of the project to modernise road infrastructure for access to the free economic zone, run by the government through the Centre Regional Development Agency. The total investment tops 25 million lei, of which about 22 million comes from the National Fund for Regional and Local Development, with the rest being Ungheni City Hall’s contribution. The works contract, signed on 13 March in Ialoveni with SRL “Aedificator”, stands at 21.93 million lei, according to MOLDPRES.

Until the works are finished, drivers who use Decebal towards the economic zone should expect restrictions and detours on the section under construction. It is an artery on which the city hall has concentrated several infrastructure projects in recent years, and the stretch to the economic zone was listed in a mayoral disposition as far back as April 2022.