TAG

#Itinera

1 article
A red crane lifting a girder segment next to a massive concrete abutment at the Prut river bridge construction site near Ungheni; to the right, a group in high-visibility vests inspects the works.
NATIONAL

A8 motorway contract to Ungheni suspended by court: 3.5 billion lei and 5 km on the Moldovan side, blocked

The Bucharest Court of Appeal suspended on August 5 the contract for the DN24–Ungheni Border section of the A8 motorway. Construction cannot begin until the disputes are resolved, with a hearing set for September 30. The approximately 5-km segment in the Republic of Moldova — from the bridge to the Ungheni bypass — is caught in the same ruling.

Ion Calmis·31 August 2026· NewsWHAT'S AT STAKE
1/3 · reporting underway· got a tip? write to us →